The first batch construction of China Hualong No. 1 reactor-the internal structure of the reactor plant of Zhangzhou Nuclear Power Unit No. 1 +16.5-meter platform concrete concrete pouring completed at 22:28 on July 2nd.
At present, the design, procurement, construction and commissioning preparations of the Zhangzhou project are under full control. The follow-up Zhangzhou Nuclear Power Unit No. 1 will open the roof at the end of October to complete the first introduction of all main equipment and dome hoisting.