The group is currently delivering two HVDC offshore transmission projects at DSMa, both of which are being constructed under contracts with Aker Solutions as the main EPCI contractor.
Work began last year and, with assembly and outfitting commenced, the first is planned for delivery in the first half of 2023, and the second will be delivered in the first quarter of 2024.
Once complete, the HVDC topsides will set sail for Aker Solutions’ yard in Stord, Norway, where the HVDC equipment will be installed and commissioned before they depart for their final destinations.
Damen is undertaking the structural fabrication, surface protection, and outfitting including insulation, lighting, ducting, local cabling, and more, as well as the fabrication of the transport grillages.
“Damen Shipyards Group is a key partner for us in offshore wind. Their facilities are well suited for fabricating these types of structures, and the company shares our passion for delivering large, complex projects safely and sustainably. We have built a very strong relationship with the company over the past years and consider Damen as an integral part in successfully delivering our HVDC portfolio”, said Arne Engevik, HVDC director at Aker Solutions.