The grapnel will be deployed to detect and remove surface debris located on the inter-array cable routes and at the wind turbine, substation topside, and jack-up locations.
The inter-array cable lay out is planned to begin on 10 April at the earliest, weather depending. For this work, DEME will deploy its newly acquired DP3 offshore installation vessel Viking Neptun.
The inter-array cables are connected to the substations in six loops (3 per OSS), whereas a single interconnector connects OSS-S to OSS-N. The laid inter-array and interconnector cables will be left unburied and unprotected on the seabed until July 2023.
The Walk-to-Work vessel, Horizon Enabler, will support these operations.
This is the first campaign of PLGR and inter-array cables lay out. There are three planned PLGR and cable installation campaigns for the inter-array cable routes, with subsequent campaigns planned between July and November 2023.
The 450 MW wind farm, jointly owned by EDF Renewables and ESB, is being built 15 kilometres off the coast of Fife, Scotland.
Neart na Gaoithe will comprise 54 Siemens Gamesa 8 MW wind turbines which are scheduled to be put into full operation in 2024.
The export cables are connected to the project’s two offshore substation jacket foundations and the commissioning of the second substation is well underway.