Search

Hydropower

Saturday
29 Jul 2023

Gilkes Commissions Hydropower Turbine at Water Treatment Plant in the US

29 Jul 2023  by waterpowermagazine   

Hydro engineers from Gilkes have recently returned from the US, successfully completing the commissioning of the company’s latest hydropower turbine in North America. The installation of the 867kW Vertical Four Jet Pelton took place at Sherard Water Treatment Plant in Wyoming.

The project aims to utilize the existing raw water pressure to power the City of Cheyenne's water treatment facility. The groundwork for this project began two years ago with the construction of a dedicated powerhouse. The turbine operates using water flows from Cheyenne's water supply as it enters the plant.

The main purpose of this hydropower system is to provide energy for the treatment plant, which typically consumes 200 to 400kW. Any surplus power generated will be channeled back to the grid, potentially benefiting the community by contributing clean energy resources.


Keywords

More News

Loading……