CEEC was awarded the EPC contract for each of the 500MW wind farms in Bash and Dzhankeldy on the 7th of December, 2022.
The successful installation of the first turbine on the Bash wind farm is just one of the many milestones that we are excited to mark on this project. Most importantly, the steady progress takes us closer to supporting and contributing to Uzbekistan’s long-term ambitions to increase the share of renewables in their energy mix.
Kashif Rana, Chief Portfolio Management Officer of ACWA Power
https://platform.twitter.com/widgets/tweet_button.2b2d73daf636805223fb11d48f3e94f7.en.html#dnt=false&id=twitter-widget-1&lang=en&original_referer=https%3A%2F%2Fwww.acwapower.com%2Fnews%2Facwa-power-installed-the-largest-wind-turbine-in-central-asia%2F&size=l&text=Kashif%20Rana%2C%20Chief%20Portfolio%20Management%20Officer%20of%20ACWA%20Power%20-%20The%20successful%20installation%20of%20the%20first%20turbine%20on%20the%20Bash%20wind%20farm%20is%20just%20one%20of%20the%20many%20milestones%20that%20we%20are%20excited%20to%20mark%20on%20this%20project.%20Most%20importantly%2C%20the%20steady%20progress%20takes%20us%20cl…&time=1691499873660&type=share&url=https%3A%2F%2Fwww.acwapower.com%2Fnews%2Facwa-power-installed-the-largest-wind-turbine-in-central-asia%2F
When complete in the first quarter of 2025, the Bash wind farm will include 79 wind turbine generators (WTG) and is expected to generate more than 1,650 GWh of electricity annually and reducing carbon dioxide emissions by 750 tonnes per year. ACWA Power has a 25-year power purchase agreement (PPA) with the JSC National Electric Grid of Uzbekistan for the project.
ACWA Power boasts an impressive portfolio of 10 projects in Uzbekistan, with a combined investment value of US$ 7.5 billion. The company’s continued investments and partnerships underline its dedication to the sustainable development of Uzbekistan’s energy landscape, promoting economic growth, and advancing the country’s renewable energy goals.