Search

Nuclear Power

Wednesday
21 Feb 2024

EDF Delays Restart of UK's Heysham 1 and Hartlepool Nuclear Reactors

21 Feb 2024  by reuters   

The logo of Electricite de France (EDF) is seen in front of electrical pylons at the Tricastin nuclear power plant site in Saint-Paul-Trois-Chateaux, France, November 21, 2022. REUTERS/Eric Gaillard/File Photo Purchase Licensing Rights
Britain's EDF Energy, owned by French utility EDF, has extended outages again at four of its UK nuclear reactors because of continuing work on steam valves, the company told Reuters.

The expected restart dates of Heysham 1-1, Heysham 1-2 and the Hartlepool 1 and 2 reactors have been pushed back by about a week to March, the firm's outage website page showed. The Heysham 1 reactors have been offline since December and the Hartlepool units have been out of action since January.

The Heysham 1 power plant, which has two reactors with combined capacity of around 1.2 gigawatts (GW), was taken offline late last year for inspections on steam valves at the boilers.

As a protective measure, the Hartlepool plant - also with two reactors with combined capacity of about 1.2 GW - was taken offline in January because it has the same reactor design.

"Since the valve issue at Heysham 1 in late December 2023 we have been carrying out modifications, replacements and safety case work for all four units with the same valves," an EDF Energy spokesperson said.

"This work is nearing completion but has needed some extra time to conclude. We have changed the restart dates to accommodate this and expect the units to start coming back into service over the coming weeks."

EDF said in January that it aims to keep four nuclear plants in Britain - Torness, Heysham 1, Heysham 2 and Hartlepool - running longer than originally planned, subject to regulatory approval, and will make a decision by the end of this year.

Last year it extended the life of its Hartlepool and Heysham 1 nuclear plants by two years to 2026.

Keywords

More News

Loading……