Repsol and Galp have asked the Federal Energy Regulatory Commission (FERC) to require U.S. LNG exporter Venture Global to disclose commissioning reports submitted to the regulator for its Calcasieu Pass LNG project.
The Arlington, Virginia-based exporter said it "opposes the requests of Repsol and Galp for confidential documents and ... will not provide any such documents unless and until explicitly ordered to do so by the Commission."
Venture on Feb. 15 asked the commission for a one year extension to complete construction of its Calcasieu Pass gas-export plant, or receive assurances the plant did not need an extension.
The company has argued that it is unable to move the plant from a commissioning phase to commercial operations because it has not finished fixing electrical problems.
Customers, including Galp and Repsol, have been denied contracted cargoes of the superchilled gas, they have said, even as Venture has sold more than 275 cargoes on the open market during what it calls the plant's pre-commissioning phase.
Repsol and Galp have asked FERC to see documents submitted by Venture to the regulator to evaluate the company's commissioning claims.
BP PLC (BP.L), opens new tab, Shell PLC (SHEL.L), opens new tab and Edison SPA (EDNn.MI), opens new tab also raised issues with the proposed extension request and have ongoing contract arbitration claims against Venture Global for its failure to deliver their cargoes.