Trans Mountain to Finish Final Segment of Oil Pipeline Expansion in April, Filing Says

03 Apr 2024  by reuters   

A pipe yard servicing government-owned oil pipeline operator Trans Mountain is seen in Kamloops, British Columbia, Canada June 7, 2021. REUTERS/Jennifer Gauthier Purchase Licensing Rights, opens new tabCompanies
Trans Mountain will finish building the final segment of its Canadian oil pipeline expansion in April, according to a construction schedule the corporation filed on Monday with a regulator.

The Canadian government-owned C$34-billion ($25.07 billion)pipeline expansion will nearly triple the flow of crude from Alberta to Canada's Pacific Coast to 890,000 barrels per day, but has been plagued by years of delays, construction problems and cost overruns.

Spread 5-B is the last segment to complete and Trans Mountain's schedule filed to the Canada Energy Regulator shows construction and testing wrapping up this month.

Trans Mountain said last month it has started filling its expanded pipeline in a staged process, but still faced technical challenges.

The pipeline, scheduled to be in service in the second quarter, is expected to raise Canadian crude prices just as producers boost production.