The plant is owned by Omaezakikou Biomass Energy G.K., an equity method affiliate of Renova.
In a statement, Renova said it has rescheduled the feed-in-tariff (FIT) period of the 75-megawatt project. It has also received liquidated damages from the EPC for a certain period of time due to the change in the commencement of commercial operation based on the contract.
Due to this change, Renova expects the revenue of Omaezakikou G.K. for the current fiscal year ending 31 March 2025 to decrease by approximately $34.95m (JPY5b). However, the impact on operating income and profits below operating income are expected to be limited.