In the EMEA region the Günstedt project has agreed to receive 10 V162-6.2 MW turbines as part of a 20 year AOM 5000 service agreement.
Delivery of the turbines has been planned for the 3Q26 with the initial commissioning start-up date scheduled for 1Q27.