Another order from Germany comes from Windpark Ohrenbach for the WP Ohrenbach project, which totals 48 MW. This project will consist of 8 V162–6.0 MW turbines and will be covered by a 20-year service agreement. Delivery is expected in the second quarter of 2026, with commissioning set for the fourth quarter of 2026.
In Latvia, Vestas has secured a 64 MW order from Ventspils Wind for an undisclosed project. This project will include 10 V162-6.4 MW turbines and a 35-year service agreement. Delivery is planned for the first quarter of 2026, with commissioning scheduled for the third quarter of 2026.